Exciting redevelopments are underway at Cayton Village Club Site

26/11/2019

Coming soon for September 2020...

Cayton Village Club Site is due to undergo an incredible multi-million pound transformation. The updates will see the development of a brand new, high-quality site kitted out with:

  • Two new, high-quality central washroom facility buildings, an enclosed playground and a multi-use games area.
  • More available touring pitches.
  • Re-designed roads and pitch layouts.
  • A brand new Premium pitch type.
  • Four service points, two drive over motor van waste points and electric vehicle charging points.
  • A refurbished the welcome desk (reception) and shop.
  • A designated dog walking area and a new mixed area for camping and campervans.


Camping, glamping and more!

The site will also be home to a number of new glamping units – perfect for Club members with extended families who want to stay in this wonderful seaside location but don’t have their own outfit.

The site will be re-opening in September 2020 and will stay open until January each year.

Take a look at the proposed site map for Cayton Village.

 

March 2020 updates:

  • The upper toilet block is now weather tight, the floor has been screed and underfloor heating installed
  • The fitting of the lower toilet block interior is well underway with floor tiles down and wall finishes are nearly complete
  • We’re continuing with laying the roads and new pitches around the site
  • Landscaping planting around the site has begun
  • The alternative accommodation bases have been laid and the paths are now going in

 

February 2020 updates:

  • The framework for the wash facilities has now gone up on the upper part of the site
  • The floor of the lower wash facilities has been screed and underfloor heating installed
  • The road and pitch bases are continuing to be worked on in the lower site
  • We are now on sale for stays from 1 August 2020 – 4 January 2021


January 2020 updates:

  • We've been busy adding a roof to the lower wash facilities, and a foundation to the upper wash facilities
  • The tractor shed timber frame is up and mechanical and electrical work is underway
  • We'll be starting road bases before moving on to excavating pitches
  • We've started forming the stone bases for the glamping units

Cayton from the air

Take a look at Cayton Village Club Site from the air - before the work began